FERC denies challenges to PJM’s fast-track power plan, paving way for roll out
Rehearing requests were denied for plan to accelerate grid connection for shovel-ready projects, despite concerns from clean energy sector.

Details:
Filing Date: April 14, 2025
Docket Numbers:
Short Summary:
FERC denied rehearing requests challenging PJM Interconnection LLC’s Reliability Resource Initiative (RRI), a plan designed to fast-track the interconnection of up to 50 new generation projects to address resource adequacy concerns, according to an April 14 notice. The rejection marks a blow to several groups, including clean energy associations that said the plan was flawed.
Impact Level:
Categories:
Entities: PJM Interconnection
Markets: PJM Interconnection (PJM)
Regions: Mid-Atlantic & Midwest
States:
Regulators: FERC
Courts: