March 11, 2025
Delays to New England grid interconnection reforms is raising alarms of a PJM-style capacity price spikes
Further delays in the approval of the market reforms could leave up to 3 GW of new resources ineligible for the next capacity commitment period, according to one estimate.

Details:
Filing Date: March 11, 2025
Short Summary:
Advanced Energy United (AEU), along with several environmental and consumer advocacy groups, has called on FERC to expedite its decision on ISO New England’s (ISO-NE) revised generator interconnection process. The reforms, compliant with FERC Order No. 2023 and which received unanimous support, aim to streamline the process, but delays in approval could jeopardize new capacity additions and impact market prices.
Impact Level:
Categories:
Entities:
Markets: ISO New England (ISO-NE)
Regions: Northeast
States:
Regulators: FERC
Courts: