May 15, 2025
FERC approves PJM grid study agreement for LS Power’s 300-MW data center
The FERC approval comes amidst a broader inquiry by the agency into PJM’s handling of co-located loads and their impact on the transmission system.
The FERC approval comes amidst a broader inquiry by the agency into PJM’s handling of co-located loads and their impact on the transmission system.
LSP Digital’s proposal to shift Doswell Generating Station’s capacity to a behind-the-meter data center faces opposition from the PJM Independent Market Monitor.
LS Power’s capacity additions would total 700-MW across the PJM footprint under the grid-operator’s Reliability Resource Initiative.
The long-term deal ensures Ravenswood power plant can switch to fuel oil, safeguarding NYC grid during gas shortages.