FERC denies key rate request for $3B Valley Link Transmission Project, launches inquiry
The split decision seeks to strike a balance between incentivizing transmission development with consumer protection, setting a potential precedent for future projects.

Details:
Filing Date: May 13, 2025
Docket Numbers:
Short Summary:
FERC approved some incentives for the 417-mile Valley Link Transmission Project, a joint venture between Transource Energy LLC (a joint venture of American Electric Power Company Inc. and Evergy Inc.), FirstEnergy Corp., and Dominion Energy Inc., while denying its proposed return on equity and initiating a rate inquiry, according to a May 13 order. The project is designed to address reliability issues in PJM arising from surging power demand from data centers.
Impact Level:
Categories:
Tags: Grid Reliability, Ratepayer Impacts, Return on Equity, Transmission Planning, Transmission Projects, Transmission Rate Incentives
Entities: American Electric Power Company Inc., Dominion Energy Inc., Evergy Inc., FirstEnergy Corp.
Markets: PJM Interconnection (PJM)
Regions: Mid-Atlantic & Midwest
Regulators: FERC