FERC greenlights Palisades Nuclear Plant restart in historic decision
The approval for interconnecting to the grid advances the first return of a nuclear plant to active service in the U.S., setting a key precedent for similar projects.

Details:
Filing Date: April 3, 2025
Docket Numbers:
Short Summary:
FERC has accepted the interconnection agreement between Holtec Palisades LLC, Michigan Electric Transmission Company LLC (METC), and MISO for the Palisades Nuclear Plant, effective Feb. 28.
Impact Level:
Categories:
Tags: Generator Interconnection Service Agreements, Nuclear, Nuclear Licensing Process, Nuclear Reactor Restart
Entities: Holtec International