June 4, 2025
FERC orders PJM to clarify land acquisition responsibility in interconnection agreements
PJM must revise its interconnection agreements to explicitly assign land acquisition duties for network upgrades to transmission owners, not customers.

Details:
Filing Date: June 2, 2025
Docket Numbers:
Short Summary:
FERC directed PJM Interconnection LLC to revise its pro forma interconnection construction service agreement (ICSA) and generator interconnection agreement (GIA) to clarify that transmission owners, not customers, are responsible for acquiring third-party land rights for network upgrades. This resolves a dispute over land acquisition responsibilities.
Impact Level:
Categories:
Tags: Generator Interconnection Queue, Generator Interconnection Service Agreements, Project Development
Entities: PJM Interconnection
Markets: PJM Interconnection (PJM)