FERC plans final decision for Golden Pass LNG gas supply lateral project for December
The project is intended to diversify the LNG terminal’s feed gas sources.

Details:
Filing Date: June 9, 2025
Docket Numbers:
CP25-205
Short Summary:
FERC announced target dates for its review of Golden Pass LNG Terminal LLC’s application to construct the Supply Lateral Project in Jefferson County, Texas. FERC plans to issue an environmental assessment (EA) by Sept. 12, followed by a 90-day period for federal authorization decisions, culminating in a final decision deadline of Dec. 11.
Impact Level:
Categories:
Tags: Environmental Review, LNG, LNG Projects, Natural Gas, Natural Gas Pipeline Projects, Project Permitting Process
Entities: ExxonMobil Corp., QatarEnergy
Markets:
Regions: Texas
States: Texas
Regulators: FERC