FERC rejects Susquehanna Nuclear rehearing on co-located load, upholding standardized interconnection rules
The decision reinforces FERC’s focus on standardized interconnection processes and the high hurdle for non-conforming agreements.

Details:
Filing Date: April 10, 2025
Docket Numbers:
Short Summary:
FERC denied Susquehanna Nuclear LLC’s rehearing request and partially granted Vistra Corp.’s motion for clarification regarding the rejected amendment to the interconnection service agreement (ISA) between PJM, Susquehanna Nuclear, and PPL Electric Utilities Corp., according to an April 10 order. In upholding its initial rejection, FERC asserted that PJM failed to demonstrate the necessity of deviating from standard procedures.
Impact Level:
Categories:
Markets: PJM Interconnection (PJM)
Regions: Mid-Atlantic & Midwest
States: Pennsylvania
Regulators: FERC