March 5, 2025
PJM moves to extend deactivation notice period amid looming wave of plant retirements
The proposal, the first change in PJM’s deactivation process in two decades, aims to improve grid reliability planning by updating generator deactivation processes in the face of increasing plant closures.

Details:
Filing Date: March 4, 2025
Docket Numbers:
Short Summary:
PJM Interconnection is seeking to extend the required notice period for generator deactivations to 12 months, up from the current period of at least three months. The proposal also eliminates a cap, currently set at $2 million, for investments associated with prolonging operations of power plants beyond the desired deactivation date.
Impact Level:
Categories:
Entities: PJM Interconnection
Markets: PJM Interconnection (PJM)
Regions:
States:
Regulators: FERC
Courts: N/A