Generator Interconnection Queue

Featured image for “MISO revises Expedited Resource Addition Study initiative, aims for August implementation”
June 8, 2025

MISO revises Expedited Resource Addition Study initiative, aims for August implementation

The revised proposal includes a project cap, stricter requirements for demonstrating need, and accommodates retail choice states, aiming to accelerate generation projects to meet resource adequacy needs.

Featured image for “MISO looks to integrate revised fast-track generator study process in joint agreement with SPP”
June 8, 2025

MISO looks to integrate revised fast-track generator study process in joint agreement with SPP

The proposed change aims to streamline the interconnection of commercially ready projects in both RTO footprints, addressing urgent capacity needs.

Featured image for “SPP seeks FERC approval to include MISO’s 2023 DPP cycle in joint targeted interconnection queue process”
June 6, 2025

SPP seeks FERC approval to include MISO’s 2023 DPP cycle in joint targeted interconnection queue process

The change aims to streamline interconnection procedures and reduce delays for new generation projects along the MISO-SPP seam.

Featured image for “SPP proposes fix to grid connection process for data centers”
June 5, 2025

SPP proposes fix to grid connection process for data centers

The new process aims to address backlog of connection requests by considering planned generation resources.

Featured image for “FERC orders PJM to clarify land acquisition responsibility in interconnection agreements”
June 4, 2025

FERC orders PJM to clarify land acquisition responsibility in interconnection agreements

PJM must revise its interconnection agreements to explicitly assign land acquisition duties for network upgrades to transmission owners, not customers.

Featured image for “SPP clears 123 generator interconnection agreements totaling 21 GW in 2024, up 32% from 2023”
May 27, 2025

SPP clears 123 generator interconnection agreements totaling 21 GW in 2024, up 32% from 2023

Shifting fuel mix sees solar, storage, and hybrid or thermal projects dominate interconnection queue, surpassing wind.

Featured image for “Southwest Power Pool plans fast-track generator study to avert looming capacity shortfall in 2027”
May 27, 2025

Southwest Power Pool plans fast-track generator study to avert looming capacity shortfall in 2027

SPP projects a 17 GW capacity shortfall by 2030, necessitating the accelerated study and integration of new projects to meet resource adequacy and reliability needs.

Featured image for “Repsol, Pattern Energy, and Illinois Generation partner on grid connection for renewable projects topping 1GW in capacity”
May 19, 2025

Repsol, Pattern Energy, and Illinois Generation partner on grid connection for renewable projects topping 1GW in capacity

The joint venture helps streamline the interconnection process, optimizing resource utilization for the developers which face long PJM project queues.

Featured image for “Western grid faces record load growth, reliability risks from data centers”
May 14, 2025

Western grid faces record load growth, reliability risks from data centers

Data centers in the Western Interconnection are dominating the grid connection queues, accounting for nearly 80% of total requests from large load customers.

Featured image for “FERC denies challenges to PJM’s fast-track power plan, paving way for roll out”
April 23, 2025

FERC denies challenges to PJM’s fast-track power plan, paving way for roll out

Rehearing requests were denied for plan to accelerate grid connection for shovel-ready projects, despite concerns from clean energy sector.

Featured image for “FERC rejects clean energy groups’ challenge to MISO grid connection overhaul for tackling major project backlog”
April 8, 2025

FERC rejects clean energy groups’ challenge to MISO grid connection overhaul for tackling major project backlog

The coalition of renewable groups contend that the grid manager’s plan will fail to resolve massive gridlocks in connecting new projects to the system, which has grown to over 300 GW.

Featured image for “FERC approves streamlined grid connection rules for New England generators amid 80% surge in requests”
April 7, 2025

FERC approves streamlined grid connection rules for New England generators amid 80% surge in requests

The order approves revised interconnection procedures, timelines, cost allocation methods, and financial security requirements for generators connecting to the New England grid, aiming to streamline the process while addressing a backlog of interconnection requests.

Featured image for “MISO aims for quicker generator review process to avert looming capacity shortfall”
March 19, 2025

MISO aims for quicker generator review process to avert looming capacity shortfall

The new process aims to accelerate the study of generation projects critical for grid reliability, as MISO faces a capacity shortfall that could grow to 4.7 GW by 2028.

Featured image for “Delays to New England grid interconnection reforms is raising alarms of a PJM-style capacity price spikes”
March 11, 2025

Delays to New England grid interconnection reforms is raising alarms of a PJM-style capacity price spikes

Further delays in the approval of the market reforms could leave up to 3 GW of new resources ineligible for the next capacity commitment period, according to one estimate.

Featured image for “FERC approves PJM’s fast-track power plan to head off looming capacity shortfall”
February 11, 2025

FERC approves PJM’s fast-track power plan to head off looming capacity shortfall

The extraordinary measure by PJM to speed up generator interconnections comes as the grid manager faces a potential 10 GW capacity gap by the end of the decade.

Featured image for “Watchdog warns FERC on surging power demands, calls for overhaul of grid rules”
December 11, 2024

Watchdog warns FERC on surging power demands, calls for overhaul of grid rules

Potomac Economics Ltd., in comments filed with FERC on Dec. 11, urged FERC to overhaul its interconnection and rate policies as massive electricity loads increasingly cluster with power generators.

Featured image for “Google to FERC: pair data centers with renewables to fix grid bottlenecks”
December 10, 2024

Google to FERC: pair data centers with renewables to fix grid bottlenecks

The tech giant is pushing for more co-location of loads with generators, arguing it’s not about cost-cutting, but faster, smarter grid integration.

Stay Ahead in Energy Markets

Get exclusive access to in-depth analysis, market insights, and expert opinions.