June 6, 2025
El Paso Electric to double power sales agreement with Freeport McMoRan
Amendment aims to establish a 200 MW ceiling on exchanges, doubling the current limit.
Amendment aims to establish a 200 MW ceiling on exchanges, doubling the current limit.
The deal aims to ensure reliable power for Amazon’s growing Ohio data center operations while protecting AES Ohio customers.
The new process aims to address backlog of connection requests by considering planned generation resources.
Data centers in the Western Interconnection are dominating the grid connection queues, accounting for nearly 80% of total requests from large load customers.
Potomac Economics Ltd., in comments filed with FERC on Dec. 11, urged FERC to overhaul its interconnection and rate policies as massive electricity loads increasingly cluster with power generators.