December 11, 2024
Talen appeals FERC’s rejection of grid pact with Amazon data center
Talen argues ‘flawed’ analysis jeopardizes U.S. energy security.

Details:
Filing Date: November 20, 2024
Docket Numbers:
Short Summary:
Talen Energy Corp.’s subsidiary, Susquehanna Nuclear LLC, filed a request for rehearing with FERC on Nov. 20, after the commission rejected amendments to a power agreement to serve a co-located Amazon data center. Susquehanna argues that FERC’s reasoning is flawed and that it wrongly rejected a mutually agreeable deal that supports U.S. economic and national security interests, particularly concerning the growing demand for data centers.
Impact Level:
Categories:
Entities: Talen Energy Corp.
Markets: PJM Interconnection (PJM)
Regions:
States:
Regulators:
Courts:
Read Also: