March 10, 2025
Xcel Energy’s $2B power line sparks legal fight from skiing enclave Aspen
Cities appeal FERC’s decision on the $2 billion transmission project, arguing unfair cost allocation.

Details:
Filing Date: March 10, 2025
Short Summary:
The exclusive skiing enclave of Aspen, along with Colorado cities Glenwood Springs, Center, and a Nebraska energy agency have filed a legal challenge in federal court against a $2-billion power line project by Xcel Energy Inc. subsidiary Public Service Company of Colorado (PSCO). The suit follows FERC’s dismissal of their complaint over allocating the project costs to ratepayers.
Impact Level:
Tags: Complaint, Petition for Legal Review, Ratepayer Impacts, Transmission, Transmission Cost Allocation
Entities: Xcel Energy Inc.
Markets:
Regions: West
States: Colorado
Regulators: FERC
Courts: U.S. Court of Appeals for the D.C. Circuit
Read Also: